07 · Critical Path
01
Syntys Data Templates
Required operational data returned
02
Data Preparation / Configuration
Validation, import and setup
03
Syntys UAT
Business validation of modules
04
UAT Findings & Resolution
Fixes and configuration updates
05
Retesting & Sign-Off
Confirmation by module owners
06
20 September Go-Live
Phase 2 release
The Phase 2 go-live is currently at risk primarily due to pending data inputs and the subsequent UAT dependency.